The University of Texas at El Paso

Phase II: May29 through August 15

  • For the second phase of the project, from May 29th through August 15th, vehicular access to University Avenue from Sun Bowl Drive will be re-opened. Except for entry and exit into parking lot S-3 across from Kelly Hall, traffic along south Sun Bowl Drive will remain northbound only.
  • Improvement of the Schuster exit ramp is expected to begin in November. The 18-month project will include a new exit ramp overpass to allow free-flowing traffic on Schuster and direct access to the campus from I-10 via University Avenue.